HURON STREET PAVING FOR 4/30/2020

Thursday and Friday schedule for paving of streets milled last week include:

Thursday 4/30/20

  • Finish paving Old Highway 14
  • 10th street from Arizona to Lincoln ave s.w.
  • Montana Ave from 18th to 16th st s.w.

Friday 5/1/20

  • Iowa ave from Market to 3rd st s.e.
  • Idaho ave from Market to 3rd st s.e.
  • Utah ave from Market to 3rd st s.e.
  • Beach ave from Market to 3rd st s.e.
  • Frank ave  from Market to 3rd st s.e.

 

ANY CARS ON THE STREET AT THE START OF OPERATIONS WILL BE TOWED AT THE OWNER’S EXPENSE. THESE STREETS WILL BE TOTALLY BLOCKED OFF DURING THE PAVING.

IF YOUR SUMP PUMP DRAINS INTO THE STREET BEING PAVED, PLEASE REROUTE IT IMMEDIATELY TO THE BACKYARD UNTIL THE STREET IS PAVED. ALSO, DO NOT USE YOUR SPRINKLER SYSTEMS DURING THIS TIMEFRAME. THIS WILL HELP EXPEDITE THE PAVING PROCESS. THE STREET MUST BE DRY BEFORE WE CAN BEGIN PAVING.