City Commission Approves New Bid For Curb, Gutter And Sidewalk Ramp Project

City CommissionThe Huron City Commission held a special session Tuesday to deal with a bid item. City Engineer Mike Wever requested the Commission rescind a previously approved bid for a curb, gutter and handicap ramp project. Wever says shortly after the bid was approved January 26th, Big O Concrete of Mitchell came back to the city…

badbid1

Wever recommended the Commission go with the next highest bid…

badbid2

Big O originally won with bid with a price of nearly 404-thousand dollars. The city’s estimate of the project was 540-thousand dollars. The second best bid belonged to Wright and Sudlow Concrete Contractors of Aberdeen. They bid 597-thousand dollars. Two other bids came in at 599 and 614 thousand dollars. Wever says they intend to go after a bid bond posted by Big O…

badbid3

Wever says the special commission meeting was called as a courtesy to the new winning bidder so they can begin to plan their summer work schedules.