The Huron City Commission meets in regular session tonight.
Commissioners will consider a 3rd Street Dam improvements construction administration amendment with Stockwell Engineers, Inc.
The firm has provided an amendment to their current design agreement to provide construction administration services and construction staking for an hourly time and materials fee in an amount not to exceed $62,459.00. This fee will be in addition to their current contract amount of $60,000.00 for design services. The construction administration and staking fee was included in the budget for the project.
Also on tonight’s agenda is the second reading of the 2019 annual appropriation budget.
The 2019 total budget is $31,500,878 , a 1% increase over 2018.
Tonight’s meeting gets underway at 5:30 pm.